Urgently construct the 500kV Nam Dinh I - Thanh Hoa line
Icon
The National Power Transmission Corporation (EVNNPT) accelerates the construction progress of the 500 kV line project of Nam Dinh I Thermal Power Plant - Thanh Hoa, belonging to the 500 kV circuit 3 line projects from Quang Trach to Pho Noi .
Once completed, the project will contribute to releasing power transmission capacity from the Central region to the North to promptly meet progress targets as directed by the Prime Minister.
Strengthen electricity security for the North in the coming years
This double-circuit 500 kV line project has a length of about 74.4 km from the 500 kV distribution yard of Nam Dinh I Thermal Power Plant to the 500 kV Thanh Hoa substation. The project goes through 3 provinces: Nam Dinh, Ninh Binh, Thanh Hoa.
This is one of four component projects of the 500kV circuit 3 line project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) with a total length of about 515 km, passing through 9 provinces.
The implementation of the project is to implement the Prime Minister's direction in Document No. 745/TTg-CN dated August 15, 2023 on the plan to ensure electricity supply in the last months of 2023 and 2024; Dispatch No. 782/CD-TTg dated September 4, 2023 of the Prime Minister on the implementation of 500 kV 3-section circuit line projects from Quang Trach to Pho Noi; Decision No. 1241/QD-TTg dated October 24, 2023 of Deputy Prime Minister Tran Hong Ha on approving the investment policy and approving the investor of the 500kV Nam Dinh I - Thanh Hoa Thermal Power Line Project; Notice of conclusion No. 440/TB-VPCP dated October 26, 2023 of Deputy Prime Minister Tran Hong Ha at the meeting on the status of investment implementation of 500 kV circuit 3 line projects from Quang Trach ( Quang Binh) to Pho Noi (Hung Yen).
Once completed, the project will help reduce the load and avoid overloading the existing 500 kV lines to ensure N-1 criteria, especially when the transmission capacity is high at the North - Central interface at the time the factories Hydropower generation in the North is low.
The project will help transmit the capacity of Nam Dinh I Thermal Power Plant after the plant comes into operation and thermal power plants in the North Central region as well as renewable energy power plants in the Central region join in. national power system, creating regional power grid connections.
In particular, after the Prime Minister's direction, Deputy Prime Minister Tran Hong Ha chaired a meeting with ministries, branches and 9 localities on the implementation of 500kV circuit 3 line projects.
Minister of Industry and Trade Nguyen Hong Dien - Standing Deputy Head of the National Steering Committee for Electricity Development chaired many meetings with the State Capital Management Committee at enterprises, EVN, EVNNPT and related localities. to discuss and agree on solutions to speed up the implementation of projects. Minister Nguyen Hong Dien has directed the Departments of Electricity and Renewable Energy and the Office of the National Steering Committee for Electricity Development to coordinate closely with EVNNPT to carry out related work in parallel according to functions, The task is to quickly complete project investment procedures.
At the same time, we request the People's Committees of the provinces where the project passes through to keep the project's route updated and agreed with EVNNPT; Complete procedures for converting rice land and forest land immediately after the project is approved; Focus on doing a good job of site clearance to hand over the clean site to the investor as soon as possible to start construction.
Work overnight, without days off to ensure project progress
Over the past time, the project investor - EVNNPT has always identified and clearly realized that this is a key and urgent project and has proactively worked with relevant ministries, branches and localities to soon complete procedures. legal framework to implement the project. The Corporation has mobilized maximum resources, working regardless of hours, overnight, without days off... to speed up project implementation.
On October 17, 2023, the General Director of EVNNPT issued Directive No. 4660/CT-EVNNPT on implementing solutions to ensure electricity supply in the last months of 2023 and 2024, which requires the Relevant units and departments urgently implement drastic and synchronous solutions to speed up the investment progress of the 500 kV line from Quang Trach to Pho Noi.
To ensure project progress according to the Prime Minister's direction, EVN and EVNNPT recommend that relevant ministries and branches continue to pay attention and provide maximum support to investors throughout the project implementation process. EVN and EVNNPT recommend that provinces where the line passes through actively create conditions and support investors to quickly complete compensation and site clearance to organize construction work.
EVN and EVNNPT request that construction contractors, design consultants, and supervision consultants urgently mobilize forces to speed up immediately after project construction, mobilize maximum resources, and give priority highest for the project to complete the project according to the striving goal.
After implementing the construction of the 500 kV line project of Nam Dinh I Thermal Power Plant - Thanh Hoa, EVN and EVNNPT continue to coordinate with ministries
Quốc Tuấn